Cooling towers at the Three Mile Island nuclear power plant in Middletown, Pennsylvania, Oct. 30, 2024.
Danielle DeVries | CNBC
MIDDLETOWN, Pa. — The owner of the Three Mile Island nuclear power plant is embarking on an ambitious plan to restart operations before the end of the decade, marking the latest chapter in the history of a plant that symbolizes the future promise, past struggles and lingering fears of nuclear energy in the United States.
The twin cooling towers that stretch hundreds of feet above the Susquehanna River just south of Middletown, Pennsylvania, went dormant in 2019 after billowing water vapor into the sky for four decades. Its owner at the time, Exelon, permanently shut down the Unit 1 reactor, citing “severe economic challenges.”
Unit 1 is one of a dozen reactors that closed in the U.S. over the past decade as nuclear industry struggled to compete against cheap and abundant natural gas. But the fortunes of the industry have shifted dramatically this year as deep-pocketed technology companies turn to nuclear power to meet the tremendous electricity consumption of their future business: artificial intelligence.
“This is a plant that we ran and ran very well,” plant manager Trevor Orth told the NRC at an Oct. 25 meeting. “We shut it down. We understand how we shut it down, and we have a good idea of how we’re going to restart this.”
The main control room of the Three Mile Island nuclear power plant in Middletown, Pennsylvania, Oct. 30, 2024.
Danielle DeVries | CNBC
While Constellation will restore the plant, it will ditch the name Three Mile Island. The plant will be rechristened the Crane Clean Energy Center, after the late CEO of Exelon, Chris Crane. Constellation said the restart will cost $1.6 billion, financed by the company’s own funds.
Microsoft has made the restart of Unit 1 possible through an agreement to purchase the full electricity output from the plant for 20 years, a sign of the growing role the tech sector is playing in shaping the future of the U.S. power industry.
Microsoft said the agreement is part of its strategy of meeting the growing electricity needs of its data centers with power that is free of carbon dioxide emissions in an effort to mitigate the impact of its business on the climate.
Part of a control panel at the Three Mile Island nuclear power plant in Middletown, Pennsylvania, Oct. 30, 2024.
Danielle DeVries | CNBC
Those data centers are playing a critical role in the U.S. economy, housing servers that run the cloud computing that businesses and consumers now rely on for life’s digital daily tasks. They are also essential for the development of artificial intelligence, technology that is viewed as critical for the nation’s future economic competitiveness and national security.
With four years until the planned restart, one of the big uncertainties is whether Constellation can deliver the power to Microsoft on time. Nuclear projects are notoriously plagued by long delays, big cost overruns and cancellations. But Unit 1 is in good condition and Constellation is confident the plant will restart on schedule, said Bryan Hanson, the company’s chief generation officer.
Most of the restoration at Unit 1 will be normal maintenance work that Constellation conducts regularly on its fleet of nuclear plants, Hanson said during an Oct. 30 tour of the plant.
“Not an ounce of concrete needs to be poured, not one piece of rebar needs to be tied, not one cable needs to be pulled. The infrastructure is here,” the executive said. “The challenge of delays — I don’t see it.”
A control panel in the main control room of the Three Mile Island nuclear power plant in Middletown, Pennsylvania, Oct. 30, 2024.
Danielle DeVries | CNBC
Constellation’s decision to restart Three Mile Island follows Holtec International’s decision to restart its Palisades nuclear plant in Michigan. Palisades is poised to become the first reactor to restart operations in U.S. history in 2025 after shutting down.
Holtec has plans to nearly double the power capacity of the facility in the 2030s by building two small modular reactors, next-generation technology that promises to make nuclear plants less costly and easier to deploy.
Amazon and Alphabet’s Google recently announced investments in small modular reactors.
While Constellation has not committed to building a small modular reactor at any of its plants yet, Hanson said the company is open to working with the tech sector to build new nuclear reactors in the U.S.
“If our customers come to us again, like a Microsoft, and say ‘we want to help you build new nuclear’ — we’ll probably join hands and figure out a way to do that,” Hanson said.
Lingering fears
Unit 1 is a short walk from the site of the worst nuclear accident in U.S. history.
The partial meltdown of the Unit 2 reactor at Three Mile Island in 1979 had a chilling effect on the development of new nuclear plants in the U.S. Unit 2 has not operated since the accident and is being decommissioned by its current owner, Energy Solutions, a private nuclear services company.
Unit 1 operated safely and efficiently before it was shut down for economic reasons, said Mike Goff, acting assistant secretary for the Office of Nuclear Energy at the Department of Energy.
But Pennsylvania state Rep. Thomas Mehaffie said his constituents have mixed feelings about the restart of Unit 1, particularly those who are old enough to remember the accident at Unit 2.
Pennsylvania state Rep. Tom Mehaffie speaks in front of the Three Mile Island nuclear power plant in Middletown, Pennsylvania, Oct. 30, 2024.
Danielle DeVries | CNBC
“Of course people who were here during that time frame, who are older — there is concern. There always has been concern,” said Mehaffie, who represents the communities around Three Mile Island at the state legislature in Harrisburg. Mehaffie’s father was a union electrician who helped build the nuclear plants.
Hanson said the nuclear industry has learned from this chapter of its history.
“The 1979 accident taught us that our standards weren’t right at the time,” Hanson said. The U.S. nuclear industry today has the best safety, reliability and operational standards in the world, he said.
While some constituents have concerns, others see the economic value that the restart will bring, Mehaffie said. The restart of Unit 1 will bring an estimated 3,400 jobs to the region, according to a study by the Pennsylvania Building & Construction Trades Council.
Grid reliability
The planned restart of Three Mile Island is also a step to help ensure the region’s electric grid remains reliable, Mehaffie said. Unit 1 will bring back 835 megawatts of carbon-free electricity, equivalent to the consumption of more than 600,000 homes, at a time when the grid is on the brink of faltering.
Electricity demand is outpacing supply, as power plants, particularly those that run on coal, are retired faster than new capacity is built, grid operator PJM Interconnection warned in July. PJM operates the grid in Pennsylvania and 12 other states.
“Grid reliability is everything,” Mehaffie said.
PJM has forecast that electricity demand will surge nearly 40% by 2039 due to the expansion of data centers, manufacturing and the electrification of industry and transportation. Meanwhile, 40 gigawatts of power generation is at risk of retirement by 2030; that’s about 21% of PJM’s installed capacity.
“We’re seeing potentially catastrophic early retirements of dispatchable resources,” Mark Christie, a commissioner at the Federal Energy Regulatory Commission, said during a public hearing Nov. 1.
A cooling tower at the Three Mile Island nuclear power plant in Middletown, Pennsylvania, Oct. 30, 2024.
Microsoft said the electricity it will be purchasing from Unit 1 will feed into the grid and will not directly power its data centers. Microsoft is committed to bolstering the grid as it secures power for its data centers, said Alistair Speirs, senior director of global infrastructure for Microsoft’s Azure cloud platform.
“When we operate in the community, if we’re not stabilizing, adding resiliency to the grid, then it’s hard for us to keep our social license to operate,” Speirs said.
Microsoft is not involved in the physical restoration of the plant, Hanson said, but Constellation is providing status reports to the company.
Restoration and restart timeline
Constellation laid out how it plans to restart the plant in the company’s first public meeting with the Nuclear Regulatory Commission on Oct. 25. While Wall Street is generally bullish on the restart, Citi has cautioned that Constellation could face challenges in completing the project on schedule.
“Given the regulatory and physical challenges, we assume that [Constellation] is likely to experience some delays and cost overruns to execute on the restart,” Citi analyst Ryan Levine told clients in an Oct. 14 note.
Citi initiated coverage of Constellation with a neutral rating in October on delay concerns. Constellation’s stock has gained more than 90% since the start of the year and 12% since the Three Mile Island restart was announced Sept. 20.
Levine is an outlier. The vast majority of analysts rate the stock a buy or strong buy, with the average price target predicting more than 23% upside.
The turbine deck of the Three Mile Island nuclear power plant in Middletown, Pennsylvania, Oct. 30, 2024.
Danielle DeVries | CNBC
Hanson said crucial and expensive equipment such as the steam generators and main power generator have undergone inspection and maintenance by Constellation and are in good condition.
The steam generators were replaced in 2009 and are ready for restart, he said. The internals of the main power generator, built by General Electric nearly 50 years ago, were replaced a little over a decade ago, he said. The main generator has been cleaned and needs some routine maintenance, he said.
The plant’s main power transformers need to be replaced at a cost of $75 million to $100 million, Hanson said. The transformers are on order with delivery expected in late 2026, he said.
One of the cooling towers has been gutted and will be refurbished. The analog control room will remain the same with the exception of some rewiring, Hanson said.
The simulator that mimics the control room also needs to be restored so plant operators can be trained there. One of the most critical items for restoring plant operations is training operators for NRC certification, a process that takes about 18 months, Hanson said.
The turbine deck of the Three Mile Island nuclear power plant in Middletown, Pennsylvania, Oct. 30, 2024.
Danielle DeVries | CNBC
Constellation is currently prohibited from operating and loading fuel into the reactor vessel because the plant was permanently shut down. Constellation plans to file an exemption request in November that would remove these restrictions if approved by the NRC.
“That will officially mark the start of our restart activities,” Dennis Moore, senior manager of licensing at Constellation, told the NRC.
Constellation plans to file a request to change the plant’s name from Three Mile Island to the Crane Clean Energy Center in February. Later in 2025, Constellation will submit filings on the plant’s technical specifications, environmental impact, emergency plan, and site security plan for NRC review, the company said.
Constellation intends to send an operational readiness letter to the NRC by July 2027. The company would then begin testing and return to power if the NRC determines that the plant is ready to operate and authorizes placing fuel in the reactor.
In the meantime, Constellation does not need NRC permission to “start turning wrenches and doing restoration work” at the plant, said Scott Burnell, a spokesperson for the regulator. The NRC will be monitoring the work to make sure the regulator’s requirements are met, Burnell said.
The restarts at Three Mile Island and Palisades will likely secure NRC approval, Goff said.
“They are an independent agency, but I expect if the safety cases are presented, they’re going to approve it,” Goff told CNBC in September.
Toyota USA has refreshed its RAV4 for 2026, and, in a significant step forward for efficiency, Toyota has axed the non-hybrid version of the vehicle. The RAV4 will now only be available in HEV and PHEV versions starting in the 2026 model year.
However, in an act of greenwashing reminiscent of many things Toyota has done before, it’s confusingly calling its vehicles “100% electrified” – despite that every single RAV4 includes a gas engine.
The improvements include new looks and trim lines, including an outdoorsy Woodland model (like the bZ just got) and a higher-performance “GR SPORT” model (though, we must remind everyone, that SUVs are not sportscars and will never be sportscars), and higher power from both PHEV and HEV models.
The PHEV model also boasts improved range, bumped from 42 miles to 50 miles – still lower than we’d typically consider worthy of coverage on Electrek, but the number is at least usable to keep the average driver on electric power for most of their daily driving (if they bother to plug it in).
Advertisement – scroll for more content
Some trims will have DC fast charging, and you’ll be able to charge from 10-80% in 30 minutes.
Notably, the RAV4 no longer includes any option for a non-hybrid powertrain. All trims are either hybrid or plug-in hybrid. Previously, it had been anticipated that an EV model might join the lineup, but it looks like Toyota is just sticking with the newly-renamed bZ model for that purpose.
Toyota calls its new RAV4 options “highly efficient electrified powertrains,” but did not specify anticipated EPA mileage numbers for the HEV model, or for the PHEV when operating on gas power. The current RAV4 hybrid gets 39mpg (that’s about 10mpg better than the non-hybrid), and we would imagine something in that ballpark for the updated model.
The 2026 RAV4 will be available in Toyota dealerships across the US “later this year.” Pricing has not yet been announced.
Electrek’s Take
But the real issue here is the use of the word “electrified,” and specifically, “100% electrified.”
Toyota has a longhistory of deceptive advertising when it comes to its electrification efforts. Its lies have gotten it in trouble before, both in Norway and in the US.
So its use of the word “electrified” should be looked at with some skepticism, since the company has used it before to confuse consumers into thinking that its vehicles are more efficient than they really are. For some previous coverage on that, see the FTC complaint filed against Toyota over its false electrification claims.
In this case, Toyota has upped the ante, not just claiming that its vehicles are electrified, but “100% electrified.”
There are a lot of terms that get used confusingly in the EV industry, oftentimes purposefully, in order to greenwash companies’ efforts. EV, PHEV, EREV, FCEV, HEV, BEV, electrified, all-electric, and so on.
But one thing that has heretofore been reserved for models that do not include a gasoline engine is any variation on “all-electric,” “100% electric,” “fully electric” or the like.
So, moving from “electrified” to “100% electrified” certainly seems like intentional phrasing by Toyota here. “Electrified” was already questionable, but “100% electrified” is well over the line.
So despite that we should be happy about a step-change improvement in powertrain availability on the RAV4, and the elimination of the non-hybrid model, Toyota just had to play one of its tricks and remind us why they’re the greatest enemy of electrification in the auto industry (well… save one).
Charge your electric vehicle at home using rooftop solar panels. Find a reliable and competitively priced solar installer near you on EnergySage, for free. They have pre-vetted installers competing for your business, ensuring high-quality solutions and 20-30% savings. It’s free, with no sales calls until you choose an installer. Compare personalized solar quotes online and receive guidance from unbiased Energy Advisers. Get started here. – ad*
FTC: We use income earning auto affiliate links.More.
Elon Musk interviews on CNBC from the Tesla Headquarters in Texas.
CNBC
Elon Musk said Tuesday that artificial intelligence development could run into power generation problems by the middle of next year, as the technology industry builds increasingly large data centers.
Musk told CNBC in an interview that his artificial intelligence startup xAI is planning a gigawatt-size facility outside Memphis, Tenn. He said the facility would be complete in six to nine months. A gigawatt is equivalent to the power capacity of the average nuclear plant in the U.S., according to the Department of Energy.
Musk said AI faces three major limitations as it scales up: chips, transformers and power generation. Transformers are used to ramp down the voltage of electricity produced by power plants so it can used by computers.
“As we solve the transformer shortage, there will be the fundamental electricity generation shortage,” Musk told CNBC’s David Faber. “My guess is people are going to start hitting challenges with power generation maybe by the middle of next year, end of next year.”
Alphabet’s Google unit warned in February that the U.S. is facing a power capacity crisis as the U.S. races against China to achieve dominance in AI. Google started looking into nuclear energy after realizing renewables were potentially causing instability on the grid, said Caroline Golin, Google’s global head of energy market development. The output of wind and solar is dependent on weather conditions.
Google ran into a “very stark reality that we didn’t have enough capacity on the system to power our data centers in the short term and then potentially in the long term,” Golin said at a February conference hosted by the Nuclear Energy Institute in New York City.
Musk said Tuesday that China is building significantly more power generation than U.S. “China power generation looks like a rocket going to orbit and U.S. power generation is flat,” the Tesla CEO said.
Musk’s xAI is using natural gas turbines to help power its Colossus data center in Memphis. Environmental advocates have accused xAI of violating the Clean Air Act and permitting requirements for “major sources of air pollution” by using gas turbines without mitigation technologies or permits in place.
Utilities such as Dominion Energy told investors on recent earnings calls that they are not seeing evidence of slowing data center demand, despite anxiety in the market that the tech sector might cut back on concerns about of a possible recession. Dominion serves the largest data center market in the world located in northern Virginia.
But Constellation Energy cautioned that although demand is strong, some of the forecasts by utilities are overstated as developers shop their data centers in multiple jurisdictions. Constellation is the largest operator of nuclear plants in the U.S.
“I just have to tell you, folks, I think the load is being overstated,” CEO Joe Dominguez said on the power company’s first quarter earnings call. “We need to pump the brakes here.”
Hyundai is shutting down a production line at its Ulsan plant in Korea, where the IONIQ 5 and Kona EV are built. Although it’s only for a few days, the move comes as the automaker faces slower exports.
Why is Hyundai pausing EV production in Korea?
For the third time this year, Hyundai is planning to pause production of some of its most popular EV models in Korea.
Industry sources said on May 20 (via Newsis) that Hyundai will shut down Line 2 at its Ulsan plant in Korea, where it builds the IONIQ 5 and Kona Electric. The pause will start on May 27 and end on May 30.
Despite launching a new discount campaign in Korea earlier this month, offering over $4,300 (6 million won) in savings on the IONIQ 5, sales are still lagging. In particular, Hyundai has exported significantly fewer IONIQ 5 models this year.
Advertisement – scroll for more content
Through April, Hyundai exported just 9,663 IONIQ 5s, down from 27,476 sold overseas in the same period last year.
Kona EV exports have also fallen sharply. Through April 2025, Hyundai shipped just 3,428 Kona EV models, down 42% from nearly 6,000 last year.
Hyundai IONIQ 5 refresh in Korea (Source: Hyundai)
According to the report, Hyundai said in an internal note, “The sluggish sales in the global electric vehicle market have not improved,” adding, “We have made every effort to secure additional orders, but we are currently unable to secure the quantity.”
Following a temporary halt in February and April, this will be Hyundai’s third time pausing EV production in Korea this year.
Hyundai Kona Electric N Line (Source: Hyundai)
In a turn of events, Hyundai’s joint venture in China, Beijing Hyundai, announced losses improved by over 100 million won ($72 million) in Q1. With its first custom-tailored electric SUV launching in China later this year, Beijing Hyundai could turn a profit by the end of 2025.
The Korean automaker reported its seventh consecutive record sales month in the US. The IONIQ 5 remains a top seller with over 12,000 units sold through April, up 14% from last year.
Hyundai IONIQ 9 three-row electric SUV (Source: Hyundai)
IONIQ 6 sales, on the other hand, are down 10% this year, with 4,424 sold through April, and Hyundai doesn’t give a breakdown for Kona EV sales.
Hyundai is also offering generous discounts in the US right now with up to $12,500 in upfront savings on the new three-row IONIQ 9. The 2025 IONIQ 5 is a steal with leases starting at just $209 per month.
Ready to try out Hyundai’s electric vehicles for yourself? We’ve got you covered. You can use our links below to find popular Hyundai EV models in your area.
FTC: We use income earning auto affiliate links.More.