Cooling towers and reactors 3 and 4 are seen at the nuclear-powered Vogtle Electric Generating Plant in Waynesboro, Georgia, U.S. Aug. 13, 2024. 

Megan Varner | Reuters

Expanding two power plants in Georgia and South Carolina with big, new reactors was supposed to spark a “nuclear renaissance” in the U.S. after a generation-long absence of new construction. 

Instead, Westinghouse Electric Co.’s state-of-the-art AP1000 design resulted in long delays and steep cost overruns, culminating in its bankruptcy in 2017.  The fall of Westinghouse was a major blow for an industry that the company had helped usher in at the dawn of the nuclear age. It was Westinghouse that designed the first reactor to enter commercial service in the U.S., at Shippingport, Pennsylvania in 1957. 

Two new AP1000 reactors at Plant Vogtle near Augusta, Georgia started operating in 2023 and 2024, turning the plant into the largest energy generation site of any kind in the nation and marking the first new operational nuclear reactor design in 30 years. But the reactors came online seven years behind schedule and $18 billion over budget.

In the wake of Westinghouse’s bankruptcy, utilities in South Carolina stopped construction in 2017 on two reactors at the V.C. Summer plant near Columbia after sinking $9 billion into the project. 

But today, interest in new nuclear power is reviving as the tech sector seeks reliable, carbon-free electricity to power its artificial intelligence ambitions, especially against China. Westinghouse emerged from bankruptcy in 2018 and was acquired by Canadian uranium miner Cameco and Brookfield Asset Management in November 2023

The changed environment means South Carolina sees an opportunity to finish the two reactors left partially built at V.C. Summer eight years ago. The state’s Santee Cooper public utility in January began seeking a buyer for the site to finish reactor construction, citing data center demand as one of the reasons to move ahead.

“We are extraordinarily bullish on the case for V.C. Summer,” Dan Lipman, president of energy systems at Westinghouse, told CNBC in an interview. “We think completing that asset is vital, doable, economic, and we will do everything we can to assist Santee Cooper and the state of South Carolina with implementing a decision that results in the completion of the site.”

Tech as a nuclear catalyst

The United States has tried to revive nuclear power for a quarter century, but the two reactors in Georgia mark the only entirely new construction across that period despite bipartisan support under every president from George W. Bush to Donald Trump.

A fresh start was supposed to have begun more than a decade ago, but was choked off by a wave of closures of older reactors as nuclear struggled to compete against a boom of cheap natural gas created by the shale revolution.

“We went from an environment in the aughts of rising gas imports and rising gas prices to fracking technology unlocking quite a bit of affordable natural gas here in the U.S., and companies didn’t really value the firm clean attribute of nuclear back then,” said John Kotek of the Nuclear Energy Institute, an industry lobby group, and former assistant secretary at the Office of Nuclear Energy under President Barack Obama.

What’s different in 2025 is the tech sector’s voracious appetite for power translating into a willingness to pay a premium for nuclear. But recent investments in nuclear have focused on restarting abandoned reactors and attempting to bring online smaller, next-generation modular reactors that many believe are the future, if they can be designed and built more cheaply.

The troubled nuclear plant at Three Mile Island near Harrisburg, Pennsylvania that almost melted down in 1979 is expected to resume operations in 2028 after owner Constellation Energy struck a power purchase agreement with Microsoft last September. Constellation wants to restart Unit 1, which shut for economic reasons in 2019, not the Unit 2 reactor that was the site of the accident.

Alphabet and Amazon invested in small nuclear reactors a month later. Meta Platforms, owner of Facebook and Instagram, asked developers in December to submit proposals for up to 4 gigawatts of new nuclear power to meet the energy needs of its data centers.

But while the recent focus in the U.S. has been on restarts and commercializing small reactors, Lipman said the extent of potential demand that has emerged from data centers over the past year has led to renewed interest in Westinghouse’s large AP1000 reactor design.

In any event, there are no operational small reactors in the U.S. today, though startups and industry stalwarts, including Westinghouse, are racing to commercialize the technology. And there only so many shuttered plants in the U.S. in good enough shape to potentially be restarted.

Gargantuan undertaking

Meanwhile, meeting the demand for power is a gargantuan undertaking. Meta’s need for new nuclear power, for example, is nearly equivalent to the entire 4.8 gigawatts of generating capacity at the Vogtle plant, enough to power more than 2 million homes and businesses. Large nuclear plants with a gigawatt or more of capacity — the size of the AP1000 — will be essential to power large industrial sites like data centers because of their economies of scale and low production costs once they’re up and running, according to a recent Department of Energy report.

Georgia Gov. Brian Kemp called for another reactor at Vogtle the same day he dedicated the plant expansion in May 2024. Southern Company CEO Chris Womack believes at least 10 gigawatts of large nuclear are needed. Southern is the parent company of Georgia Power which operates Vogtle.

“The people that are going to own and operate AP1000s traditionally are investor-owned electric utilities,” Lipman said. “When they look at the marketplace for a large reactor, AP1000 is where they turn because it’s got a license, it’s operational.”

Still, nobody in the U.S. is on the verge of signing an order for a new AP1000, he said. Westinghouse is focused on deploying reactors in Eastern and Central Europe, where nuclear projects are seen as a national security necessity to counter dependency on Russian natural gas after the invasion of Ukraine.

FILE PHOTO: In this Sept. 21, 2016, file photo, V.C. Summer Nuclear Station’s unit two’s turbine is under construction near Jenkinsville, S.C., during a media tour of the facility.

Chuck Burton | AP

In addition to the two units in Georgia, Westinghouse also has four operational reactors in China.

But South Carolina’s search for someone to complete the partially built reactors at V.C. Summer will likely draw investment from Big Tech “hyperscalers” building data centers, and large manufacturers like the auto industry, Lipman said.

“That kind of asset attracts industry that relies on 24/7, 365 energy and that’s what you get with an AP1000,” Lipman said. There are ongoing discussions within the industry about whether the tech sector might act as a developer that invests capital in the upfront costs of building new plants, he said.

What went wrong in the South

Any attempt to build new AP1000s in the U.S. again will almost certainly meet with skepticism after the experiences in South Carolina and Georgia.

Lipman said the challenges that the AP1000 construction faced in the South have been resolved. Back then, Westinghouse agreed to the projects before the reactor design was complete, and supply chains weren’t fully formed due to a long period in which U.S. construction was dormant, he said.

“One big lesson learned, maybe the big lesson learned, is designs need to be complete before they hit the field, meaning they have to be shovel ready,” Lipman said. The design for the AP1000 is complete and Westinghouse has its supply chain in place, he said.

“We have winnowed over our list of suppliers,” Lipman said. “They are supporting us globally, and so it’s really easy then to have them make more equipment for deployment.”

“You’re getting economies of scale,” he said.

Why the U.S. has a hard time building nuclear reactors

Ironically, given the overruns in Georgia, the original aim of AP1000 was reduce costs by creating a standardized design that requires less construction materials compared to older reactor types, Lipman said. Components of the plant are prefabricated before being assembled on site, he said.

“You basically assemble, kit-like, major portions of the plant in a modular fashion, a bit like aircraft and submarines are done,” Lipman said. “That was not fully shaken out completely at the Vogtle site.”

The Department of Energy under the Biden administration argued in a September report that future AP1000 builds should be less expensive because they won’t incur costs associated with the first-of-a-kind project in Georgia. Support from the department’s loan office, tax credits under the Inflation Reduction Act, and shorter construction timelines would substantially reduce costs, according to the report.

Trump plans for nuclear

While President Donald Trump is supportive of nuclear, it’s unclear whether the industry will receive support through DOE loans and the investment tax credit under the Inflation Reduction Act (IRA). Those tools were pillars of the Biden administration’s plan to help reduce the cost of new AP1000s.

Trump issued an executive order on his first day in office that directed federal agencies to remove obstacles to development of nuclear energy resources. The same order, however, paused all spending under the IRA. Two weeks later, Secretary of Energy Chris Wright made commercializing “affordable and abundant nuclear energy” a priority in a Feb. 5 order.

US Energy Sec. Chris Wright on natural gas reduction, nuclear energy and more

“The long talked about nuclear renaissance is finally going to happen, that is a priority for me personally and for President Trump and this administration,” Wright told CNBC in a Feb. 7 interview. Wright was previously a board member of Oklo, a nuclear startup that aims to disrupt the status quo of the industry by deploying micro reactors later this decade.

Wright emphasized commercializing small reactors and said private capital would drive the construction of new plants. Before the November election, Trump was skeptical of building large reactors, citing the cancelled project in South Carolina.

“They get too big and too complex and too expensive,” he told Joe Rogan in an October interview.

Lipman said the first Trump administration was pro-nuclear, and he expects the president will support the industry in his second term.

“If there’s going to be gigawatt scale deployment in the U.S., decision making needs to accelerate,” Lipman said. “The business model, the investment climate, any legislative changes that might be in the offing at the state level or the federal, now is the time to address those pertinent issues.”

CNBC’s Gabriel Cortes contributed to this report.

Continue Reading

Environment

400 kW DC fast charging On The Run arrives in Canada – and it’s FREE!

Published

on

By

400 kW DC fast charging On The Run arrives in Canada – and it's FREE!

British Columbia got its first 400 kW DC fast charger last week at Canadian C-store chain On The Run, but that’s not the good part. As part of a limited time offer, these chargers are FREE!

The Canadian convenience store chain just took the wraps off its new, ABB-developed, 400 kW chargers earlier this month, but they’re already planning to bring the ultra-fast 400 kW dispensers to at least four more locations in BC this spring, and have them online just in time for the summer road trip season – something On The Run hopes its customers will appreciate.

“The A400 charger delivers an enhanced customer experience, with reliability and performance from a 32-inch screen to higher power charging sessions and power sharing,” reads the company’s official announcement, via LinkedIn. “Download the Journie Rewards app to start the charge – free for a limited time.”

On The Run’s new 400 kW ABB DC fast chargers are compatible with CCS and CHAdeMO plugs, and can accommodate Tesla and other NACS-equipped vehicles with an adapter. That said, the company seems to imply that Tesla drivers in particular will have a maximum charging speed of “just” 50 kW, which feel hilarious (given the current state of affairs between Tesla and the Canadian government), but probably isn’t.

Advertisement – scroll for more content

In addition to the ABB A400 400 kW units shown here, On The Run locations also employ the ABB Terra 184 dispensers rated at 180 kW. On The Run plans similar deployments at the four BC locations mentioned above, as well as two more each in Quebec and Ontario slated to go live towards the end of this year.

Electrek’s Take

Tesla’s controversial CEO Elon Musk once mocked 350 kW charging speed as being “for a child’s toy,” despite the fact that, nearly nine years later, his own cars and Superchargers can barely make it to 325 kW while others have sailed right on past. I made fun of that fact on the Quick Charge episode shown, above – and, while I do think it’s funny and relevant, the much more relevant piece of news here is that companies like BP Pulse, Revel, and Wallbox are actively deploying 400 kW solutions, today (while others hit the same mark as far back as 2017).

It’s just a fact: Tesla has fallen way behind.

SOURCE | IMAGES: On The Run, via Electric Autonomy.

FTC: We use income earning auto affiliate links. More.

Continue Reading

Environment

Terawatt opens its first electric charging truck stop in California

Published

on

By

Terawatt opens its first electric charging truck stop in California

Terawatt Infrastructure‘s first medium- and heavy-duty electric charging truck stop in California is now online, in Rancho Dominguez.

Located 12 miles north of the ports of Long Beach and Los Angeles, the private Rancho Dominguez site, which is shared among multiple fleets, will support electric trucking fleet operations in and out of the largest container ports in the US.

First customers include Dreaded Trucking, Hight Logistics, PepsiCo, Quick Container Drayage, Southern Counties Express, Tradelink Transport, and WestCoast Trucking & Warehousing.

Terawatt’s electric charging truck stop features 20 pull-through and bobtail DC fast charging stalls with a capacity of 7 megawatts (MW), enabling charging for up to 125 trucks per day using a simple reservations system. Terawatt’s site features a proprietary charge management system, in-house technicians, 24/7 customer service, and onsite parts management.

Advertisement – scroll for more content

“This launch underscores growing collaboration between enterprises, shippers, carriers, and charging infrastructure providers to advance sustainable technologies across logistics and transportation operations, especially in the medium and heavy-duty sectors,” said Neha Palmer, CEO and cofounder of Terawatt. Palmer added that the company will bring another charging site online in Rialto, California, in June.

Terawatt joined some of the world’s largest shippers and carriers in September 2024 to launch the I-10 Consortium heavy-duty EV operations pilot, the “first-ever US over-the-road electrified corridor.” Terawatt is providing charging infrastructure, including software, operations, and maintenance support at six of its owned charging hubs along the I-10 corridor.


If you live in an area that has frequent natural disaster events, and are interested in making your home more resilient to power outages, consider going solar and adding a battery storage system. To make sure you find a trusted, reliable solar installer near you that offers competitive pricing, check out EnergySage, a free service that makes it easy for you to go solar. They have hundreds of pre-vetted solar installers competing for your business, ensuring you get high quality solutions and save 20-30% compared to going it alone. Plus, it’s free to use and you won’t get sales calls until you select an installer and share your phone number with them.

Your personalized solar quotes are easy to compare online and you’ll get access to unbiased Energy Advisers to help you every step of the way. Get started here. –trusted affiliate link*

FTC: We use income earning auto affiliate links. More.

Continue Reading

Environment

Trump admin halts $5 billion NY offshore wind project mid-build

Published

on

By

Trump admin halts  billion NY offshore wind project mid-build

In its most aggressive attack against offshore wind yet, the Trump administration halted the $5 billion Empire Wind 1, already under construction off New York’s coast.

Norwegian developer Equinor announced yesterday that it received notice from the Bureau of Ocean Energy Management (BOEM) ordering Empire Wind 1 to halt all activities on the outer continental shelf until BOEM has completed its review. Interior Secretary Doug Burgum posted this tweet yesterday:

Burgum gave no indication of what insufficiencies there were in the approval process for the fully permitted offshore wind project, despite Trump’s recent declaration of a national energy emergency that speeds up permitting processes.

The commercial lease for the 810-megawatt (MW) Empire Wind 1’s federal offshore wind area was signed in March 2017 during the first Trump administration. It was approved by the Biden administration in November 2023 and began construction in 2024.

Advertisement – scroll for more content

The project is being developed under contract with the New York State Energy Research and Development Authority (NYSERDA). Empire Wind 1, which was due to come online in 2027, has the potential to power 500,000 New York homes.

“Halting construction of fully permitted energy projects is the literal opposite of an energy abundance agenda,” said American Clean Power Association CEO Jason Grumet in a statement. “We encourage the administration to quickly address perceived inadequacies in the prior permit approvals so that this project can complete construction and bring much-needed power to the grid.”

As Electrek reported, Equinor secured $3 billion to finance Empire Wind 1 in January. The total amount drawn under the project finance term loan facility as of March 31 was around $1.5 billion. 

As of March 31, Empire Wind has a gross book value of around $2.5 billion, including South Brooklyn Marine Terminal (pictured above), which was expected to become the US’s largest dedicated port facility for offshore wind.

In response to BOEM’s stop work order, New York Governor Kathy Hochul issued the following statement:

Every single day, I’m working to make energy more affordable, reliable and abundant in New York and the federal government should be supporting those efforts rather than undermining them. Empire Wind 1 is already employing hundreds of New Yorkers, including 1,000 good-paying union jobs as part of a growing sector that has already spurred significant economic development and private investment throughout the state and beyond.

As Governor, I will not allow this federal overreach to stand. I will fight this every step of the way to protect union jobs, affordable energy and New York’s economic future.

Equinor says it’s considering appealing BOEM’s order.


To limit power outages and make your home more resilient, consider going solar with a battery storage system. In order to find a trusted, reliable solar installer near you that offers competitive pricing, check out EnergySage, a free service that makes it easy for you to go solar. They have hundreds of pre-vetted solar installers competing for your business, ensuring you get high-quality solutions and save 20-30% compared to going it alone. Plus, it’s free to use and you won’t get sales calls until you select an installer and you share your phone number with them.

Your personalized solar quotes are easy to compare online and you’ll get access to unbiased Energy Advisers to help you every step of the way. Get started here. –trusted affiliate link*

FTC: We use income earning auto affiliate links. More.

Continue Reading

Trending