Keith Heyde stands on site in Abilene, Texas, where OpenAI’s Stargate infrastructure buildout is underway. Heyde, a former head of AI compute at Meta, is now leading OpenAI’s physical expansion push.

OpenAI

It wasn’t how Keith Heyde envisioned celebrating the holidays. Rather than hanging out with his wife back home in Oregon, Heyde spent late December visiting potential data center sites across the U.S.

Two months earlier, Heyde left Meta to join OpenAI as the head of infrastructure. His job was to turn CEO Sam Altman’s ambitious compute dreams into reality, seeking out vast swaths of land suitable for expansive facilities that will eventually be packed with powerful graphics processing units for building large language models.

“My in-between Christmas and New Year’s last year was actually mostly spent looking at sites,” Heyde, 36, told CNBC in an interview. “So my family loved that, trust me.”

His life in 2025 has only gotten more intense.

Since January, OpenAI has been quietly soliciting and reviewing proposals from around 800 applicants hoping to host the next wave of its Stargate data centers, AI supercomputing hubs designed to train increasingly powerful models.

Roughly 20 sites are now in advanced stages of diligence, with massive tracts of land under review across the Southwest, Midwest and Southeast. Heyde said tax incentives are “a relatively small part of the decision matrix.”

The most important factors are access to power, ability to scale, and buy-in from local communities.

“Can we build quickly, is the power ramp there fast, and is this something where it makes sense from a community perspective?” he said.

Heyde leads site development within OpenAI’s industrial compute team, a division that’s swiftly become one of the most important groups inside the company. Infrastructure, once a supporting function, has now been elevated to a strategic pillar on par with product and model development.

With traditional data centers nearly at max capacity, OpenAI is betting that owning the next generation of physical infrastructure is central to controlling the future of AI.

Inside OpenAI's data center site search

The energy needs are hard to fathom. A gigawatt data center requires the amount of power needed for some entire cities. Late last month, OpenAI announced plans for a 17-gigawatt buildout in partnership with OracleNvidia, and SoftBank.

New sites will have to include all sorts of energy options, including battery-backed solar installations, legacy gas turbine refurbishments and even small modular nuclear reactors, Heyde said. Each site looks different, but together they form the industrial backbone OpenAI needs to scale.

“We’ve done this wonderful piece of bottleneck analysis to see what types of energy sources actually allow us to unlock the journey that we want to be on,” Heyde said.

A good chunk of the capital is coming from Nvidia. The chipmaker agreed to invest up to $100 billion to fuel OpenAI’s expansion, which will involve purchasing millions of Nvidia’s GPUs.

‘Perfect wasn’t the goal’

Heyde, a former head of AI compute at Meta, helped oversee the buildout of Meta’s first 100,000 GPU cluster.

In addition to power, OpenAI is assessing how quickly it can build on a site, the availability of labor and proximity to supportive local governments, according to Stargate’s request for proposal.

Heyde said the team has made around 100 site visits and has a short list of sites in late-stage review. Some will be brand new builds, and others will require conversions and refurbishments of existing facilities. Flexibility will be key.

“The perfect parcels are largely taken,” Heyde said. “But we knew that perfect wasn’t the goal — the goal for us was, number one, a compelling power ramp.”

Competition is fierce.

Meta is building what may be the largest data center in the Western Hemisphere — a $10 billion project in Northeast Louisiana, fueled by billions in state incentives. CEO Mark Zuckerberg raised the top end of the company’s annual capital expenditure spending range to $72 billion in July.

The steel frame of data centers under construction during a tour of the OpenAI data center in Abilene, Texas, U.S., Sept. 23, 2025.

Shelby Tauber | Reuters

Amazon and Anthropic are teaming up on a 1,200-acre AI campus in Indiana. And across the country, states are rolling out tax breaks, power guarantees, and expedited zoning approvals to attract the next big AI cluster.

OpenAI is a relative upstart, having been around for just a decade and only known to the mainstream since launching ChatGPT less than three years ago. But it’s raised mounds of cash from the likes of Microsoft and SoftBank, in addition to Nvidia, on its way to a $500 billion valuation.

And OpenAI is showing it’s not afraid to lead the way in AI. A self-built solar campus in Abiliene, Texas, is already live.

While OpenAI still leans on partners like Oracle, OpenAI Chief Financial Officer Sarah Friar told CNBC last week in Abilene that owning first-party infrastructure provides a differentiated approach. It curbs vendor markups, safeguards key intellectual property, and follows the same strategic logic that once drove Amazon to build Amazon Web Services rather than rely on existing infrastructure.

However, Heyde indicated that there’s no real playbook when it comes to AI, particularly as companies pursue artificial general intelligence (AGI), or AI that can potentially meet or exceed human capabilities.

OpenAI's stealth site search drew more than 800 bids since January 2025

“It’s a very different order of magnitude when we think about the type of delivery that has to happen at those locations,” he said.

Some applicants, including former bitcoin mining operators, offered existing power infrastructure, like substations and modular buildouts, but Heyde said those don’t always fit.

“Sometimes we found that it’s almost nice to be the first interaction in a community,” he said. “It’s a very nice narrative that we’re bringing the data center and the infrastructure there on behalf of OpenAI.”

The 20 finalist sites represent phase one of a much larger buildout. OpenAI ultimately plans to scale from single-gigawatt projects to massive campuses.

“Any place or any site we’re moving forward with, we’ve really considered the viability and our own belief that we can deliver the power story and the infrastructure story associated with those sites,” Heyde said.

He understands why many people are skeptical.

“It’s hard. There’s no doubt about it,” Heyde said. “The numbers we’re talking about are very challenging, but it’s certainly possible.”

WATCH: OpenAI’s $850 billion buildout contends with grid limits

OpenAI’s $850 billion buildout contends with grid limits

Continue Reading

Environment

First Solar opens a Louisiana factory that’s 11 Superdomes big

Published

on

By

First Solar opens a Louisiana factory that’s 11 Superdomes big

First Solar just cut the ribbon on a huge new factory in Iberia Parish, Louisiana, and it dwarfs the New Orleans Superdome. The company’s $1.1 billion, fully vertically integrated facility spans 2.4 million square feet, or about 11 times the size of the stadium’s main arena.

The factory began production quietly in July, a few months ahead of schedule, and employs more than 700 people. First Solar expects that number to hit 826 by the end of the year. Once it’s fully online, the site will add 3.5 GW of annual manufacturing capacity. That brings the company’s total US footprint to 14 GW in 2026 and 17.7 GW in 2027, when its newly announced South Carolina plant is anticipated to come online.

The Louisiana plant produces First Solar’s Series 7 modules using US-made materials — glass from Illinois and Ohio, and steel from Mississippi, which is fabricated into backrails in Louisiana.

The new factory leans heavily on AI, from computer vision that spots defects on the line to deep learning tools that help technicians make real‑time adjustments.

Advertisement – scroll for more content

Louisiana Governor Jeff Landry says the investment is already a win for the region, bringing in “hundreds of good-paying jobs and new opportunities for Louisiana workers and businesses.” A new economic impact analysis from the University of Louisiana at Lafayette projects that the factory will boost Iberia Parish’s GDP by 4.4% in its first full year at capacity. The average manufacturing compensation package comes in at around $90,000, more than triple the parish’s per capita income.

First Solar CEO Mark Widmar framed the new facility as a major step for US clean energy manufacturing: “By competitively producing energy technology in America with American materials, while creating American jobs, we’re demonstrating that US reindustrialization isn’t just a thesis, it’s an operating reality.”

This site joins what’s already the largest solar manufacturing and R&D footprint in the Western Hemisphere: three factories in Ohio, one in Alabama, and R&D centers in Ohio and California. Just last week, First Solar announced a new production line in Gaffney, South Carolina, to onshore more Series 6 module work. By the end of 2026, the company expects to directly employ more than 5,500 people across the US.

Read more: First Solar pours $330M into a new South Carolina solar factory


If you’re looking to replace your old HVAC equipment, it’s always a good idea to get quotes from a few installers. To make sure you’re finding a trusted, reliable HVAC installer near you that offers competitive pricing on heat pumps, check out EnergySage. EnergySage is a free service that makes it easy for you to get a heat pump. They have pre-vetted heat pump installers competing for your business, ensuring you get high quality solutions. Plus, it’s free to use!

Your personalized heat pump quotes are easy to compare online and you’ll get access to unbiased Energy Advisors to help you every step of the way. Get started here. – *ad

FTC: We use income earning auto affiliate links. More.

Continue Reading

Environment

Chevy previews a sporty new EV, but will it actually come to life?

Published

on

By

Chevy previews a sporty new EV, but will it actually come to life?

No, it’s not the new Bolt. GM’s design team previewed a new high-riding “sporty Chevrolet EV” that should be brought to life.

Is Chevy launching a new sporty EV?

This is the all-electric vehicle Chevy should sell in the US. General Motors’ design team released a series of sketches previewing a sporty new Chevy EV.

Although it kinda looks like the new 2027 Chevy Bolt EV as a higher-sitting compact crossover SUV, the design offers a fresh take on what it should have looked like.

The new Bolt is essentially a modernized version of the outgoing EUV model with a similar compact crossover silhouette. Nissan adopted a similar style with the new 2026 LEAF as buyers continue shifting from smaller sedans and hatchbacks to crossovers and SUVs.

Advertisement – scroll for more content

Will we see the sporty Chevy EV in real life? It’s not likely. For one, the “exploration sketch” is by GM China Advanced designer Charles Huang.

GM Design posted the sketches on its global social media page, but the caption read “Sporty Chevrolet EV for the China Market.”

It’s too bad. The Bolt could use a sporty sibling like an SS variant. Chevy introduced the Blazer EV SS (check out our review) for the 2026 model year, its fastest “SS” model yet. Packing up to 615 horsepower and 650 lb-ft of torque, the Chevy Blazer SS can race from 0 to 60 mph in 3.4 seconds when using Wide Open Watts (WOW) mode.

Will the Bolt be next? I wouldn’t get my hopes up. And if GM does bring the sporty Chevy EV to life, it will likely only be sold in China. Like all the fun cars these days.

Chevy-sporty-new-EV
The 2027 Chevy Bolt EV RS (Source: Chevrolet)

What do you think of the design? Would you buy one of these in the US? Let us know your thoughts in the comments.

While deliveries of the 2027 Bolt are set to begin in early 2026, Chevy is offering some sweet deals on its current EV lineup, including up to $4,000 off in Customer Cash and 0% APR financing for 60 months.

Ready to test drive one? You can use our links below to find Chevy Equinox, Blazer, and Silverado EVs at a dealership near you.

FTC: We use income earning auto affiliate links. More.

Continue Reading

Environment

Podcast: Electricity is the base currency, Tesla Robotaxi crashes, new Porsche Cayenne EV, and more

Published

on

By

Podcast: Electricity is the base currency, Tesla Robotaxi crashes, new Porsche Cayenne EV, and more

In the Electrek Podcast, we discuss the most popular news in the world of sustainable transport and energy. In this week’s episode, we discuss electricity becoming the base currency, Tesla Robotaxi crashes, the new Porsche Cayenne EV, and more.

The show is live every Friday at 4 p.m. ET on Electrek’s YouTube channel.

As a reminder, we’ll have an accompanying post, like this one, on the site with an embedded link to the live stream. Head to the YouTube channel to get your questions and comments in.

After the show ends at around 5 p.m. ET, the video will be archived on YouTube and the audio on all your favorite podcast apps:

Advertisement – scroll for more content

We now have a Patreon if you want to help us avoid more ads and invest more in our content. We have some awesome gifts for our Patreons and more coming.

Here are a few of the articles that we will discuss during the podcast: